Transportation Design

I-95 Express Lanes D/B Phase 3B-1 from SW 10th St. to Glades Rd.

Client: FDOT District 4 PRINCE Contracting / WSP
Location: Broward County, Florida
Construction Cost: $102 Million

PHD is supporting PRINCE and WSP with transportation design services for Maintenance of Traffic for this Design-Build project.

This project involves converting the existing I-95 HOV Lanes to Managed Lanes and widening to provide two tolled Express Lanes in each direction.

The MOT consists of (3) phases:

We developed an innovative MOT solution that eliminated all temporary bridge construction. This was accomplished by shifting the mainline alignment which eliminated impacts to the existing ITS hub.

Think like PRINCE and WSP... Think Big!

I-95 Express Lanes D/B Phase 3B-1 from SW 10th St. to Glades Rd.